|
GO Transit to improve service along
Lakeshore East
Published:
August 22, 2008
Source: Government of Canada
Printer friendly version
TORONTO
— Recently completed improvements to GO Transit's Lakeshore East rail
line will relieve congestion and reduce delays for the 44,700 riders who
use the corridor each weekday.
The $69.5 million Lakeshore East corridor expansion projects included
the construction of a third track on the main rail line from Danforth GO
Station to Scarborough GO Station. This additional track will improve
train service, increasing the efficiency of the commute for the
passengers who travel along the corridor.
To improve efficiency, GO Transit has also introduced 12-car passenger
trains, the longest in North America, allowing over 300 new riders per
train.
"GO Transit is a critical service for commuters throughout the GTA and
our government is working closely with the province and GO officials to
make it more efficient," said Jim Flaherty, Minister of Finance and
Minister Responsible for the GTA. "These investments in GO Transit,
along with our long-term transportation plan FLOW, will help create a
seamless transit system that will reduce traffic congestion, improve the
environment and increase productivity."
In addition to track expansion and longer trains, bridges at Warden,
Danforth, St. Clair and Eglinton Avenues were expanded to accommodate
the additional track, and the pedestrian overpass at Woodrow Avenue was
replaced. Station, tunnel and platform improvements were made at
Eglinton, Scarborough and Danforth GO Stations, including lengthening
platforms to accommodate 12-car GO trains.
"With the completion of the third track along GO's Lakeshore East line,
GO trains will be able to keep moving as they pass other trains that are
causing delays," said Ontario Transportation Minister Jim Bradley. "Not
only are we easing congestion for GO passengers, we are building a
greener, more sustainable transportation system."
The Lakeshore East line runs from Union Station East to Oshawa. The
expansion projects along the corridor began in October 2005 and were
completed with the tunnel installation work at Scarborough Station at
the end of July. In addition to the expansion projects, GO Transit
continues to make operational improvements at Scarborough Station that
will increase the accessibility of the station for passengers using
mobility devices. This work is expected to be completed in the summer of
2009.
"Our ridership numbers have been increasing as more and more people are
choosing GO Transit," said Greg Ashbee, GO TRIP's Rail Expansion Program
Manager. "At the end of the day, we are always working to keep up with
increasing ridership numbers and to provide the most efficient and
reliable service possible."
Over a billion people have taken the GO Train or the GO Bus since GO
Transit began operating in May 1967. Today, GO Transit carries more than
50 million passengers annually or nearly 200,000 passengers on a typical
weekday.
The Lakeshore East Corridor expansion projects are part of the GO
Transit Rail Improvement Program (GO TRIP), a $1 billion-dollar
expansion initiative funded by the federal and provincial governments
and local municipalities through the Canada Strategic Infrastructure
Fund.
A backgrounder with further information on the Canada Strategic
Infrastructure Fund and GO TRIP projects is attached.
BACKGROUNDER - GO TRANSIT IMPROVEMENT PROJECTS
The Canada Strategic Infrastructure Fund supports large-scale projects
of major national and regional significance. Through this fund, the
federal and provincial governments agreed to provide up to $385 million
each to support major GO Transit rail infrastructure improvements over
seven years. Municipalities in the Greater Toronto and Hamilton Area
will also provide funding.
GO Transit carries more than 170,000 passengers an average of 32
kilometres every day on its rail system. During rush hour, almost every
seat on all GO trains is occupied. The expansion will enable GO to
accommodate more than 40,000 additional passengers forecast to use the
system during peak periods by 2011.
The GO Transit Rail Improvement Program (GO TRIP) includes 12 GO rail
projects across the system and an expansion of the GO bus network. Most
of these projects are underway, with completion expected in 2012. Below
is an update for each project.
Lakeshore West corridor
A third track is being added on two sections of the Lakeshore West
corridor to allow more GO Train service and reduce delays:
* Port Credit Station (Mississauga) to Kerr Street (Oakville):
Construction began in April 2007 and is expected to be complete by
November 2009.
* Burlington Station to Bayview Junction (Hamilton): Construction on
this portion of the corridor was completed in April 2008. All-day
service to Aldershot Station began in September 2007.
In April 2008, GO Transit implemented 12-car trains along the Lakeshore
West corridors. The addition of the two rail cars has enabled each
12-car train to accommodate 300 new riders per train – an increase of 20
per cent.
Prior to the introduction of the new, longer trains, station platform
extensions were constructed at Port Credit, Clarkson, Oakville and
Aldershot on the Lakeshore West corridor.
Lakeshore East corridor
Improvements to accommodate three-track operation between Union Station
and Scarborough Station were completed in April 2008. Further work was
done to extend the station platforms at Scarborough, Eglinton and
Danforth stations to accommodate 12-car train service.
Milton corridor
In April 2008, GO Transit implemented 12-car trains along the Milton
rail corridors. The addition of the two rail cars has enabled each
12-car train to accommodate 300 new riders per train – an increase of 20
per cent.
Prior to the introduction of the new, longer trains, station platform
extensions were constructed at Milton, Meadowvale, Cooksville, Erindale,
Kipling and Dixie on the Milton corridor. The platform extension at
Streetsville Station is currently underway.
A new storage site was built near Milton Station to accommodate longer
12-car trains and improve operational efficiencies. This allows trains
to be stored closer to where they start and finish in order to minimize
delays and reduce unnecessary train trips. The site has been operational
since January 2007.
Stouffville corridor
Construction began in May 2006 on a GO rail underpass that will allow GO
Transit to avoid delays caused by freight train traffic.
While this project is expected to be complete by December 2008, most of
the work related to the underpass has been completed and recently the
first GO Train passed through the new depressed corridor. As a result,
GO Train service along this corridor is more efficient and passengers
can expect fewer delays.
Georgetown corridor — West Toronto Diamond
Construction is underway on the West Toronto Diamond rail-to-rail grade
separation. This rail underpass will allow GO trains to avoid delays
caused by conflicts with freight trains. Preliminary works are complete,
and the construction of the grade separation is expected to begin in
early 2009, with a forecast completion date of spring 2011.
Georgetown South (Weston corridor)
An individual environmental assessment is underway to identify
improvements required to accommodate increased GO Train frequency and
options for transportation link between Union Station and Pearson
International Airport.
Georgetown North corridor
Construction began in fall 2006 to increase track capacity along the
corridor, accommodate two new rush-hour trains and provide limited
off-peak service to the Mount Pleasant GO station in North Brampton.
Construction is expected to be complete by July 2009.
Bradford corridor
The Snider rail-to-rail grade separation at the CN York subdivision
freight line has been operational since December 2006. This GO Train
rail overpass allows GO Transit to avoid delays caused by conflicts with
freight trains.
Improvements along the Bradford corridor to accommodate rail service to
Barrie are also complete and service has been operational since December
17, 2007. During the week, four morning trains depart from the new GO
Transit Barrie South Station to Union Station, and four afternoon trains
depart from Union Station to the City of Barrie.
Union Station Rail Corridor Program
GO Transit awarded the contract for the signal improvements in 2007.
Design work began in December 2007, with overall completion expected in
2014. The work on this project will include a complete replacement of
the 70-year-old track signal system at Union Station.
Additional improvements to Union Station are also underway, including
new tracks and platforms. This will help improve the efficiency of the
train network and increase operational capacity.
The Don Yard has been redeveloped by GO Transit for its daytime train
storage needs and is fully operational.
Other service areas
On September 4, 2007, two new GO Bus routes to Guelph were implemented
as part of the GO TRIP program. In addition, on June 30, 2008, GO
Transit bus service was extended to Stoney Creek.
|